War Damage to South Pars Gas Field Fully Repaired
WANA (Oct 13) – Repairs to Iran’s South Pars gas field following damage caused by the war have been completed, restoring the damaged production capacity to service, Acting Oil Minister Hamid Bovard announced on Tuesday.
Bovard said the overhaul work at the South Pars gas field, which is required due to war-related damage, has been completed, marking the end of the process to restore the field’s affected production capacity.
Earlier, Ahmad Zeraatkar, deputy oil minister for planning, said that measures taken have enabled around 50 percent of the damaged capacity at South Pars to return to service by the end of September, with production resuming in that section.
Meanwhile, fuel reserves at power plants have reached 90 percent, marking a 25-percent increase compared with the same period last year.
The measures are expected to help ensure a stable energy supply and reduce the gap between electricity supply and demand during the winter, as the country approaches the cold season.